Development Status

Current status

  • 2008. 05. : Designation of free economic zone
  • 2012. 03. : Designation of vendor
  • 2015. 04. : Hold initiation ceremony of construction
  • 2015. 05. : Initiation of basic and implementation designs for the access road
  • 2015. 09. : Initiation of arterial highway construction
  • 2015. 10. : 1st selling lots
  • 2016. 03. : 2nd selling lots
  • 2018. 05. : Initiation of the access road construction
  • 2020. 08. : Approval of partial completion of construction for 1st step (1-4 step, 357,000㎡ out of 2,839,493.8㎡)
  • 2021. : Completion of 1st step project planned
  • 2022. : Completion of 2nd step project planned

Location

 

Aerial view

Land Use Map

Lots for Sale

Land Usage

(㎡)

 
Industrial Facilities Area Research Facilities Area Work facility Area Commercial Facilities Area Neighborhood Facilities Area Housing construction Area Logistics Facilities Area Public Infrastructure Facility Area Total
1,656,856.2 224,371.8 52,661.0 102,805.5 54,170.5 97,263.8 123,174.8 1,532,629.7 3,834,226.4
43% 5.8% 1.4% 2.7% 1.4% 2.5% 3.2% 39.7% 100%